Thailand’s energy investors hope for issue resolutions

Apr 23rd at 08:01
23-04-2025 08:01:54+07:00

Thailand’s energy investors hope for issue resolutions

While Vietnam’s efforts to maintain dialogue with foreign energy developers have been acknowledged, the country’s lack of regulatory certainty remains a critical challenge, especially for Thai investors who are voicing concerns over fairness, timing, and protection.

Supa Waisayarat, head of the Power and Energy Working Group under the Thai Chamber of Commerce in Vietnam (ThaiCham), told VIR that despite ongoing engagement, Thai investors remain concerned about the lack of clear outcomes on key issues such as payment resolution and feed-in tariff (FiT) policy.

“While we appreciate the authorities’ willingness to listen, concrete results are still limited,” Waisayarat said following the April 10 working session with the Renewable Energy Task Force under the Ministry of Industry and Trade (MoIT). “We are still awaiting definitive guidance on payment settlements and clarity on FiT policy.”

The meeting, chaired by Tran Hoai Trang of the Electricity and Renewable Energy Authority, gathered major Thai developers such as B.Grimm Power, Gulf, Gunkul, Eternity, and Super Energy, representing more than 3GW of renewable capacity in Vietnam.

Central to investor frustration is the retroactive application of the certificate of commissioning acceptance (CCA) as a condition for determining commercial operation date (COD) and tariff eligibility.

According to ThaiCham, more than 2GW of existing Thai-backed projects now face the risk of losing FiT1 status, while another 700MW are classified under transitional pricing schemes, threatening venture viability.

Nguyen Anh Tuan, CEO of B.Grimm Power Vietnam, told local media that the requirement for a CCA was never clearly mandated as a precondition for COD recognition under earlier regulations. According to Tuan, this requirement only emerged after the government inspectorate issued a conclusion in November 2023, which retroactively interpreted the CCA as a necessary legal basis for determining COD and FiT eligibility.

“We were not informed that the CCA was a prerequisite. It’s only recently that this was retroactively added to the compliance conditions,” he said. “If we had known, we would have met the requirement. But applying it after the COD and using it to reclassify FiT eligibility creates major financial distress,” Tuan explained.

He added that such reclassification, moving projects from FiT1 to FiT2 or transitional rates, would slash initiative revenues by up to 50 per cent, placing severe pressure on debt servicing. Many projects may not survive this adjustment, Tuan said, noting that B.Grimm’s projects were developed and financed based on FiT1 assumptions.

Other investors echoed similar concerns. Tran Minh Tien of Eternity said the company’s projects in Ninh Thuan and Phu Yen provinces were financed by Thai and Vietnamese banks under FiT1 terms, with BIDV and Vietcombank providing guarantees. “If we are pushed to a lower FiT bracket, we won’t be able to repay the loans, and this could have knock-on effects on the financial institutions involved,” Tien said.

Meanwhile, Gulf Vietnam’s CEO, Purin Veravattanadej, noted that payment delays had persisted since January for some projects with post-COD CCAs. “We have experienced two years of temporary pricing and inconsistent payments. We are under severe cashflow stress and unable to access new credit lines due to regulatory uncertainty,” he stated.

Investors also pointed to broader implementation challenges, such as prolonged delays in land clearance, overlapping zoning between energy and mineral plans, and slow approvals for investment policy adjustments. These factors are contributing to further delays in project commissioning, with developers unable to complete COD procedures or access grid connections in time.

Despite these challenges, ThaiCham has reiterated its commitment to Vietnam’s long-term energy goals and net-zero ambitions.

“Vietnam remains a strategic market for Thai investors,” said ThaiCham’s Waisayarat. “But to continue investing confidently, we need predictable and fair regulatory frameworks, including the honouring of signed power purchase agreements (PPAs) and legal commitments.”

To support the resolution of ongoing issues, the Power and Energy Working Group of ThaiCham submitted a set of key recommendations to the MoIT. These include a formal guarantee from the government to uphold tariff commitments under all signed PPAs, the establishment of a transparent and time-bound mechanism for addressing overdue payments, and the streamlining of procedures related to licensing, land use, and grid connection for transitional renewable energy projects.

The MoIT has reaffirmed its role as a facilitator rather than an arbitrator in commercial matters. During the April 10 session, Trang tated that while the MoIT would not interfere in PPA enforcement, the ministry is revising Power Development Plan VIII and preparing task forces to support local regulatory issues.

According to the MoIT, relevant cases must follow a legal process and be reported in full to higher levels of government. “These issues require a holistic resolution. We are compiling a comprehensive report to submit,” Trang said.

Electric Power Trading Company, an arm of Vietnam Electricity (EVN), also stated that temporary payments are being applied in accordance with inspection findings, and that operation and maintenance costs are being covered while awaiting MoIT guidance. However, EVN emphasised that investors must ensure full legal compliance and maintain accurate documentation.

While regulatory agencies have shown intent to support renewable energy investment, developers remain cautious. The uncertainty has already prompted some developers to delay new commitments or redirect investment to other ASEAN markets with more stable regulatory environments, Waisayarat of ThaiCham said.

“Thai investors express hope that continued dialogue will lead to workable solutions. We believe in Vietnam’s green development vision and the potential of its renewable energy sector,” Waisayarat added. “We stand ready to work with the government in good faith to resolve these issues for the benefit of all stakeholders.”

EVN has been tasked with reviewing each project and confirming that those failing to meet feed-in tariff conditions due to investor shortcomings will not qualify for preferential tariffs. Relevant ministries and agencies shall have to resolve outstanding issues in the next month and report to the government and Politburo in June.

VIR

- 15:09 22/04/2025



RELATED STOCK CODE (2)

NEWS SAME CATEGORY

Vietnamese exporters reinvent solutions on US’s 90-day pause on reciprocal tariffs

Many industry experts view this challenge as a chance to restructure production process and enhance competitiveness.

Institute outlines three scenarios for VN's agricultural growth amid potential US reciprocal tariffs

Total export turnover of agricultural, forestry and fishery products in Q1 reached US$15.7 billion, up 13.1 per cent year-on-year.

Procedure delays loom over solar ventures

Though a newly issued electricity price framework offers a basis for initial financial calculations, investors remain cautious as multiple regulatory and procedural...

Brazil becoming key market for Việt Nam's seafood

Brazil is quickly becoming a key market for Vietnamese seafood products, presenting strong opportunities for growth, according to the Việt Nam Association of...

Việt Nam to diversify markets for agricultural products amid global trade shifts

According to the Ministry of Agriculture and Environment (MAE), Việt Nam’s agricultural product exports are inevitably affected by disruptions in global supply...

Starbucks reserve concept returns to HCM City

Starbucks Vietnam officially reintroduces its reserve concept in HCM City with the opening of the Starbucks Reserve Bitexco in HCM City.

Revised national energy plan prioritises renewables and grid upgrades

The revised Power Development Plan VIII (PDP8), approved on April 15, marks a policy shift towards cleaner energy and modern infrastructure, targeting up to 165GW...

Businesses from 50 provinces and cities to gather for Green – Kind Market’s 9th anniversary in HCM City

The Business Study and Assistance Centre (BSA Centre) in collaboration with the Southern Agricultural Trade Promotion Centre will host a series of special events in...

US farm produce to Việt Nam will rise with import tariff cut

A wide range of US agricultural products will soon enter the Vietnamese market at more competitive prices, following a significant reduction in import tariffs.

AEON Vietnam breaks ground on new project in Hai Duong

On April 19, AEON Vietnam held the construction commencement ceremony for the AEON Hai Duong shopping centre, which is scheduled to open in 2026. The shopping...


MOST READ


Back To Top