Vinacomin says losses at bauxite project will last four years

Aug 25th at 14:41
25-08-2014 14:41:11+07:00

Vinacomin says losses at bauxite project will last four years

The Vietnam Coal and Mineral Industries Holding Corporation (Vinacomin) has said that its Tan Rai bauxite mining and processing project in the Central Highlands will incur losses for up to four years upon the start of its operations last October, instead of two years as previously calculated.

In its report reviewing one-year alumina production released last week, Vinacomin said it has revised the financial performance of the Tan Rai project in the Central Highlands province of Lam Dong, based on the actual operations of the project since October 1 last year.

According to the latest calculation of the group, the net present value (NPV) of the project is more than VND2.9 trillion and the internal rate of return (IRR) is around 6.86-8.59%.

These figures are lower than those in the joint report of Vinacomin and the Ministry of Industry and Trade sent to the National Assembly in May, and much lower than the ministry’s prediction at the time when the Tan Rai project started.

In its revised calculation, Vinacomin also said the project will rack up losses for four years, instead of two years as stated in its May report, and need 11.5 years to recoup investment capital compared to 12-13 years as predicted previously by the industry-trade ministry.

The group explained that it cannot ensure a good balance sheet for the project in the first four years and can only pay the loan interest and part of the principal although the selling price has been higher than production cost.

However, depreciation and loan interest are not factored into selling prices, and the group will have to use another source of income to cover bauxite losses.

After scaling up investment in the Tan Rai project by 30% early last year, Vinacomin announced an annual loss of around VND176-258 billion in the project.

Despite losses, Vinacomin still affirms that the project’s NPV will increase, the period of accumulated losses will be shortened, and the time for recouping capital is shorter.

The group also keeps its forecast for pre-tax profit at VND161 billion per year and payment to the State budget inclusive of charges and fees at VND400 billion per year.

In reality, it paid only around VND100 billion to the State budget last year and the target of VND400 billion can only be achieved when the project operates in a stable manner.

Also in its latest report, Vinacomin puts forward two reasons that will help bring good business results for the project, which are the corporate income tax being slashed from 25% to 20%, and that Indonesia, the biggest alumina provider for China, has stopped its shipments since this year, leaving a big chance for Vietnam.

The group exported 251,000 tons of alumina in the first seven months, raising the total export volume of the product to 411,000 tons in the period from June last year up to date.

FOB (free-on-board) export prices of alumina have been raised to US$330-340 per ton since early this year as the product quality has been improved.

Vinacomin expects a total export volume of 150,000 tons for China-based Yunnan Copper Company Limited year. It has also signed a contract to ship around 200,000 tons of alumina to Japan’s Marubeni Corporation.

vietnamnet



NEWS SAME CATEGORY

Vietnam’s sole refinery in talks with Gazprom Neft on expansion plan

The operator of the Dung Quat Refinery, Vietnam’s sole oil refinery, is in talks with a leading Russian oil producer over a plan to increase the facility’s...

Leading state-owned machinery firm to go public in 2015

On August 13 the Minister of Construction approved the equitisation roadmap of the Vietnam Machinery Installation Corporation (Lilama).

Vietnam ends contract with Chinese contractors who unilaterally quit power project

The operator of a multimillion-dollar hydropower project in Vietnam’s Central Highlands announced Wednesday it had terminated an agreement with two Chinese...

South Korean investors eye thermal power plant

The Korea Electric Power Corporation (KEPCO) has shown interest in investing in the Song Hau 3 thermal power plant, a major project in the Mekong Delta province of...

HP sales inch up while profit drops

Hewlett-Packard on Wednesday (Aug 20) reported that its quarterly revenue rose for the first time in three years, nudged by improved computer sales everywhere...

E-commerce sees rapid growth

 The Ministry of Industry and Trade's Viet Nam E-Commerce and Information Technology Agency (VECITA), has said that total sales for the e-commerce sector have...

Vietnam, US conceive nuclear family

Lightbridge has become the first American company to invest in Vietnam’s fledging civil nuclear power industry.

Atlantic retreats from $1b plan

An overly complicated and lengthy approval process has forced Australian mining company Atlantic Ltd to exit an aluminium supply chain project in the Central...

Vinacomin ships more than 400,000t of aluminium

The Lam Dong Aluminium-Bauxite Complex Project run by the Viet Nam Coal and Mineral Industries Group (Vinacomin) has exported 411,000 tonnes of aluminium since...