Energy generation, incomes surge ahead

Aug 21st at 12:59
21-08-2012 12:59:16+07:00

Energy generation, incomes surge ahead

Electricity developer Lao Holding State Enterprise (LHSE) reported that electricity generation by the Nam Theun 2 (NT2) hydropower project reached 3,338GWh in the first six months of this year.

“It is 59.03 percent of the yearly plan,” The LHSE General Manager Dr Somboune Manolom said on Friday.

LHSE was established in February 2005 and its first investment was in the NT2 hydropower project, in which it holds a 25 percent share in the Nam Theun 2 Power Company Limited.

The generated energy from NT2 is mainly exported to the Electricity Generating Authority of Thailand (EGAT) with the balance going to Electricite du Laos (EDL).

Speaking at the company's biannual meeting in Vientiane, Dr Somboune said that of the total power generated, 3,179GWh was sold to EGAT and 159GWh was supplied to EDL.

The first six months export to EGAT was 59.38 percent of the annual target and the supply to EDL was 53 percent of the whole year's target.

“NT2 is expected to generate 5,654GWh for supply to the two customers this year, with 5,354GWh going to Thailand and 300GWh for EDL,” Dr Somboune said.

In the first six months, the export income earned by NT2 from energy sales to Thailand was over US$54.6 million plus an additional almost 2.5 billion Thai baht.

It also made earnings through selling to EDL over US$2.9 million and another 115.5 million Thai baht.

“The total income was more than 1.1 trillion kip (US$139 million). The NT2 also paid royalties of almost US$7 million to the government,” Dr Somboune said.

He also said that in the first six months, LHSE received the first dividend of this year amounting to almost US$7.6 million, which was 21.51 percent larger than initial expectations. LHSE also paid dividend tax of US$759,450 to the Ministry of Finance.

LHSE had repaid in principal and interest over US$2.2 million to the ministry against a loan taken out by LHSE for its NT2 investment.

NT2 is the single largest project ever developed in Laos with an installed capacity of 1,070 megawatts (MW).

LHSE is a business entity of the Lao government for investment in electric power. It has followed a path of rapid growth in the power sector during the seven years it has been in operation.

Now it is a shareholder in nine power plant construction projects with installed capacity of 5,393MW and the ability to generate about 29,220 million kWh annually.

The nine hydropower plants in which LHSE has a stake are NT2, Nam Ngum 3, Xe Pian-Xe Nam Noi, Nam Ngiep 1, Nam Theun 1, Xekong 4, Xekong 5, Nam Kong 1 and Hongsa Thermal Electric Power

vientiane times



NEWS SAME CATEGORY

International competitive bidding to start for northern power grid

Electricite du Laos (EDL) will find out which company will be the winner to develop the Greater Mekong Subregion (GMS) Northern Power Transmission Project on the...

Power exports surpass expectations, but local consumption drops

Electricite du Laos (EDL)says this year's energy supply for local consumption will be less than originally planned while the exports will be much larger than...

Power purchases exceed expectations

Electricite du Laos (EDL) says this year's energy purchases, including imports and supplies from local generators, will be much larger than initial expectations...

Govt assumes 10 percent ownership of Phu Bia

The Lao government has taken ownership of a 10 percent share of the Phu Bia Mining Company, one of the major mining operations in the country.

Govt's power plant development surges ahead

Three construction projects for government-owned hydropower plants, the Houay Lamphan Gnai, Nam Khan 2 and the Nam Sana, are progressing steadily after building...

Japanese composite products have construction market potential

With the sustained economic growth in Laos, Japanese business executives are optimistic about the market potential for their Japanese made wood and plastic...

Unprocessed timber exports continue unabated

Laos has a policy to add more value to Lao timber products before exporting them, however it is not easy to put the policy into practice as most of the local wood...

Major hydropower plants to be completed this year

Three major hydropower plant construction projects in Luang Prabang and Xieng Khuang, Borikhamxay and Xekong provinces are progressing well and expect to reach...

Low prices mean struggles for Vientiane fish farms

Vientiane fish farms are being more adversely affected by low prices than by the customary numbers of fish that die in the nets due to the high level and poor...

Electric transmission tower factory to open in Laos

Th e first high-voltage electric transmission line tower factory is set to begin production in Laos, to supply both the domestic market and those of neighbouring...