Govt's power plant development surges ahead

Aug 9th at 12:44
09-08-2012 12:44:31+07:00

Govt's power plant development surges ahead

Three construction projects for government-owned hydropower plants, the Houay Lamphan Gnai, Nam Khan 2 and the Nam Sana, are progressing steadily after building works began last year and all three anticipate starting commercial operations on schedule.

The three projects are located in Xekong province, Luang Prabang province and Vientiane province respectively. They will all be operated by Electricite du Laos (EDL), on behalf of the government.

EDL Managing Director Mr Sisavath Thiravong reported at the recent biannual meeting in Vientiane that the construction of Houay Lamphan Gnai is now more than 32 percent complete, work at the Nam Khan 2 is 27 percent complete, and the development at Nam Sana is about 14 percent complete.

The Houay Lamphan Gnai construction officially began in May last year. The project is an investment of about 1.6 trillion kip (US$206 million).

The investment capital is being provided by the state-owned EDL through a loan from a Chinese bank. The loan is to be repaid within 15 years after the dam becomes operational.

The project contractor is the China Gezhouba Group Company Limited (CGGC). By 2015 the dam will be generating electricity for the southern provinces, where the demand for power is increasing rapidly. It will take about 5 years to build the power station, which will have a capacity of 88 megawatts (MW) and generate 480 million kWh per year.

The Nam Khan 2 construction project on the Khan River bega n in December last year, with commercial operation expected to co mmence in 2015.

Mr Sisavath said that the project involves a total investment of about 2.4 trillion kip (US$308 million), of which 95 percent has been borrowed from the Exim Bank of China, while the balance comes from EDL's coffers.

The government expects to repay the entire sum borrowed from Exim bank within 15 years. Construction is being carried out by the Chinese company Sinohydro.

The project will have an installed capacity of 130MW and will be able to generate 558 million kWh of electricity per year.

EDL signed an engineering procurement and construction contract for the Nam Sana project with Nawarat Patanakarn Public Company Limited of Thailand in June last year.

EDL's investment in the project will be about 241 billion kip (US$30 million). The money for the investment was secured in the form of a loan from a Thai bank. The loan was approved in 2010 and EDL will have 10 years to repay it.

The commercial operation of the power station is expected to begin in early 2014. The plant will have a capacity of 14MW that will generate about 49.6 million kWh per year.

The electricity generated will be carried on EDL's grid of 22KV voltage transmission lines and will supply Kasy district.

The recent biannual report noted that currently there are 15 hydropower plants that have an installed capacity of 2,519.70MW, including EDL-Gen's 7 plants with an installed capacity of 381MW, and state owned EDL's 4 plants with 3.70MW. The remaining 4 plants are being operated by independent power producers.

vientiane times



NEWS SAME CATEGORY

Japanese composite products have construction market potential

With the sustained economic growth in Laos, Japanese business executives are optimistic about the market potential for their Japanese made wood and plastic...

Unprocessed timber exports continue unabated

Laos has a policy to add more value to Lao timber products before exporting them, however it is not easy to put the policy into practice as most of the local wood...

Major hydropower plants to be completed this year

Three major hydropower plant construction projects in Luang Prabang and Xieng Khuang, Borikhamxay and Xekong provinces are progressing well and expect to reach...

Low prices mean struggles for Vientiane fish farms

Vientiane fish farms are being more adversely affected by low prices than by the customary numbers of fish that die in the nets due to the high level and poor...

Electric transmission tower factory to open in Laos

Th e first high-voltage electric transmission line tower factory is set to begin production in Laos, to supply both the domestic market and those of neighbouring...

Acer computer centre opens in Laos

A customer support centre for Acer computers was officially opened in Vientiane last Saturday, aiming to penetrate the rapidly growing IT market in Laos.

Tapioca plant expansion project on schedule

The Lao Indochina Group Public Company Tapioca Factory's production capacity expansion project to accommodate the large supply of raw cassava in the coming fiscal...

Crop exports continue to rise in Laos

Income from the export of commercial crops continues to grow every year and investment in the agricultural sector has also increased.

IFC and Korean company to develop hydropower in Laos

International Finance Corporation (IFC), a member of the World Bank Group and Korea Western Power Co., Ltd, have jointly agreed to develop sustainable hydropower in...

Seminar paves the way for bitumen plant in Laos

The Lao government hopes to persuade a Lao bitumen supplier and its Thai counterpart to enter into a joint venture to construct a bitumen processing plant here in...


MOST READ


Back To Top