LNG power plant projects risk falling behind schedule

1h ago
06-10-2026 08:03:58+07:00

LNG power plant projects risk falling behind schedule

Of the 18 liquefied natural gas (LNG) power plant projects with a total capacity of over 20,000 MW, only two have commenced construction, and only the Hiep Phuoc LNG project is assessed as likely to be on schedule.

17 of 18 LNG power plant projects face the risk of being behind schedule

17 of 18 LNG power plant projects face the risk of being behind schedule. Photo: chinhphu.vn

This was reported at the first meeting of the steering committee for key projects in the fields of industry, trade, and construction took place on October 1.

At the meeting, Deputy Minister of Industry and Trade Truong Thanh Hoai stated that key energy projects are currently distributed across different stages and there are significant discrepancies in progress.

Of the 18 LNG power plant projects under monitoring with a total capacity of over 20,000 MW, 16 projects have completed the investor selection process, while the remaining two projects, namely Nghi Son LNG and Long Son LNG, still have not selected investors.

Even in May, Nghi Son Economic Zone Management Authority had to cancel the bidding to select the investors for the Nghi Son LNG-fired thermal power plant for the third time, as zero dossiers were submitted.

Of the 16 projects that already have investors, only two have actually commenced construction, while 14 are still in the process of finalising investment preparation steps.

Minister of Industry and Trade Le Manh Hung stated that only the Hiep Phuoc LNG project is considered likely to meet the schedule.

In March, EVN and Hiep Phuoc Power Co., Ltd. signed the Power Purchase Agreement (PPA) and held a groundbreaking ceremony for the plant in Hiep Phuoc commune, Ho Chi Minh City. This is the second PPA in the LNG power sector in Vietnam, following the Nhon Trach 3 and 4 projects.

It is also the first LNG PPA implemented under Decree No.56/2025/ND-CP, which establishes preferential mechanisms for imported LNG power plant development. The event marks a step forward in completing the legal framework and boosting LNG power projects in Vietnam.

Meanwhile, the vast majority of the remaining projects are facing numerous obstacles related to investment preparation procedures, land clearance, capital arrangement, and negotiations of PPAs, along with accompanying technical conditions.

Due to the unique nature of the gas-electricity chain, delays in one component risk directly affecting the entire supply chain. Therefore, the Ministry of Industry and Trade is required to have a thorough review of each project's completion capacity to promptly develop appropriate alternative power source options, ensuring national energy security.

At the meeting, Deputy Prime Minister Pham Gia Tuc requested the development of specific timelines for each energy project, from investment preparation and decision-making to the selection of engineering – procurement - construction contractors and commercial operation date (COD).

DPM Tuc noted that monitoring and supervision should not only be based on the final COD milestone but should also track each stage throughout the entire implementation process to identify and address pending issues early.

VIR

- 09:00 03/10/2026



RELATED STOCK CODE (1)

NEWS SAME CATEGORY

Why logistics will define the next phase of growth

For more than a decade, Vietnam has been one of the main beneficiaries of shifting global manufacturing activity. Companies have expanded production across the...

ESG for future-ready industrial success

As Vietnam accelerates its industrial transformation, Soilbuild International is helping redefine the country’s industrial real estate landscape by adapting...

Stavian IP accelerates its modern expansion

Stavian Industrial Park is speeding up the expansion of a network of modern and integrated industrial parks across Vietnam, targeting a land bank of around 5,000...

Central Retail to invest $23 million in GO! shopping centre in Gia Lai

The project, scheduled to begin in the first quarter of 2027, covers nearly 15,000sq.m and has a total investment of more than VNĐ600 billion (US$23 million).

Measures to be taken to remove barriers for power investment

The Ministry of Industry and Trade plans to submit a revised Law on Electricity to the National Assembly at its October session, aiming to remove investment...

Nghi Sơn refinery builds alternative crude sources amid geopolitical risks

NSRP is broadening its crude supply base to reduce exposure to Middle East disruptions, while higher refining margins and increased capacity helped the refinery...

GreenYellow and Vina Paper partner on rooftop solar project

As energy costs remain a significant consideration for paper manufacturers, GreenYellow is supporting Vina Paper to accelerate its energy transition through a 2.036...

SOTRANS targets chemical warehousing growth with Ho Nai project

As safety, environmental, and supply chain transparency standards become increasingly stringent, building a chemical warehouse is no longer simply a matter of...

Construction begins on a rice processing complex linked to biomass energy in Mekong Delta

The project will use modern processing technology to improve the quality of export rice while making use of rice husks, a major by-product of milling, as biomass...

UNIQLO expands sustainability initiatives in Việt Nam

Japanese global apparel retailer UNIQLO and its parent company, Fast Retailing, continue to advance a corporate growth model aligned with sustainable development.


MOST READ


Back To Top