Investors and legislation at odds on energy contracts

Mar 27th at 13:56
27-03-2025 13:56:00+07:00

Investors and legislation at odds on energy contracts

Liquefied natural gas projects in Vietnam are facing bankability challenges which affect the country’s efforts in energy reform.

Under Decree No.56/2025/ND-CP, issued on March 3, elaborating on the Electricity Law about power development, grid development strategy, investment of power projects, and the tendering process for selecting power investors, imported liquefied natural gas (LNG) power schemes must secure a minimum contract quantity (Qc) of at least 65 per cent of the average power generation during the loan repayment period, capped at 10 years post-commercial operation date.

However, Vietnam Electricity (EVN) said that LNG imported power investors want to be committed to Qc at 72-90 per cent for the entire contract term. This request comes from lenders to ensure stable cash flow for investors to repay their debts.

LNG fuel suppliers and transporters also often request regulations on mobilisation rates to ensure stability in fuel quantity and price in the long term. This also helps them plan international sea transport, especially when Vietnam is a new and small market for international LNG suppliers.

“However, accepting the Qc condition of 72-90 per cent as proposed by investors will pose a risk of increasing electricity prices,” EVN commented.

According to EVN’s calculations, LNG gas has a high cost, at $12-14/million BTU when imported to Vietnamese ports. Thus, the cost of electricity generation of a gas-fired power plant using imported LNG fuel will be much higher than other power sources. With high electricity generation costs, large fluctuations, and long-term output commitment requirements, EVN’s input electricity purchase costs will be greatly impacted, strongly affecting the retail price of electricity output.

However, to avoid the risk of power shortage, EVN believes that it is necessary to clearly define Qc through a long-term contract to ensure the harmony of interests of all parties and has proposed that the prime minister decide on an appropriate rate during the debt repayment period of the project with a proposed rate of about 65 per cent.

EVN is negotiating power purchase agreements with Nhon Trach 3 and Nhon Trach 4 projects, but they have not yet agreed on the level of commitment to purchase electricity output from these plants.

A representative of one foreign bank said that if the PPA requires the clause, it will be difficult for investors to borrow capital because foreign banks will be unable to accept it.

“If the investor himself has other sources of income from the LNG power project or is guaranteed by a multi-industry parent company, it will be easier to borrow from foreign financial institutions, even with the clause. However, if there is only cash flow from the project itself, foreign banks will find it difficult to lend,” he said.

When implementing a large and complicated project, there may be a point where procedures are not completed promptly. If the inspection agency considers it a violation of regulations and retroactively applies, the project’s cash flow will no longer be as originally planned. Investors also have no other source to repay the debt, so the feasibility of repaying is not strong.

“Foreign investors often set up a business to implement the project and borrow under project financing without guarantees, so banks will be no different from investors. If they only have cash flow to repay debt from the PPA, it will be difficult for them,” he added

During a working trip to South Korea by the leaders of the central province of Quang Tri last year, on accelerating the progress of Hai Lang LNG project, the investors requested the provincial People’s Committee to urge top-level leaders to approve the appropriate electricity output consumption rate of the project, with a Qc level of 85-90 per cent, to ensure the feasibility of capital arrangement.

In addition, the investors requested early approval of the connection plan and acceleration of the completion of the power line and transformer station, ensuring compliance with the commercial operation progress of the project and paying attention to supporting the site clearance work.

VIR

- 12:54 27/03/2025



RELATED STOCK CODE (1)

NEWS SAME CATEGORY

​Samsung Ho Chi Minh City complains about not receiving $22.9 million in VAT refunds

Samsung Electronics HCMC CE Complex (SEHC) has not received value-added tax (VAT) refunds of more than VND582 billion (US$22.9 million), causing difficulties in the...

Enterprises strengthen environmental responsibility through EPR implementation

The implementation of Extended Producer and Importer Responsibility (EPR) regulations is a crucial step in enhancing corporate accountability in waste management...

Việt Nam's agricultural exports face quality control obstacles

Strict regulations in key export destinations require businesses to meet international standards, while the country's reliance on raw material exports limits...

Vietshrimp international aquaculture fair begins, featuring over 200 booths

The fair runs for three days from March 26 to 28, with over 200 booths from nearly 150 domestic and international businesses and organisations.

​Ho Chi Minh City generates handsome tourism revenue in Q1

Ho Chi Minh City’s tourism sector earned VND56.662 trillion (US$2.2 billion) in January-March, a 26.7-percent increase from the same period last year, driven by...

Quảng Trị breaks ground on $9.2 million inland port project

The Vsico Quảng Trị Inland Port aims to develop a logistics hub with warehouses, yards, technical infrastructure and equipment to provide cargo handling, storage...

562 firms win Vietnamese high-quality goods award

The 2025 Vietnamese High-Quality Goods awards were conferred on 562 firms operating in various sectors at a ceremony in HCM City on March 25.

Vietnam’s manufacturing revolution: unlocking smart factory potential with Abeam Consulting

ABeam Consulting is helping manufacturers to switch to smart factory solutions and optimise production processes in Vietnam.

​Hanoi welcomes over 7mn tourists in Q1, earns nearly $1.2bn

Hanoi welcomed 7.3 million visitors and earned an estimated VND29.93 trillion (US$1.17 billion) in revenue in January-March, according to a Hanoi...

Work begins on two construction material plants in Huế

In his speech at the groundbreaking ceremony, chairman of the Huế City People's Committee, Nguyễn Văn Phương, said these two key projects are expected to drive...


MOST READ


Back To Top