US sanction on contractor delays Long Phu 1 thermal power plant​​​​​​​

Oct 30th at 09:53
30-10-2018 09:53:44+07:00

US sanction on contractor delays Long Phu 1 thermal power plant​​​​​​​

Long Phu 1 thermal power plant is riddled by uncertainties around international loans as the project contactor is subject to sanctions from the US.

PetroVietnam has sent documents to the Ministry of Industry and Trade (MoIT) to update and report about the implementation and problems at Long Phu 1 Thermal Power Plant project.

Accordingly, by September 2018, the overall progress of the engineering, procurement and construction (EPC) contracts of the joint venture between Power Machines (PM) and PetroVietnam Technical Services Corporation (PTSC) reached 77.01 per cent compared with the target 99.35 per cent.

Also, in the documents sent to the MoIT, PetroVietnam proposed to increase the investment by VND11.6 trillion ($504.35 million). Explaining the reasons, PetroVietnam cited a range of cost increases (see table).

The project is currently running 18 months behind schedule and may be delayed by at least 36 months as the contractor Power Machines from Russia has been sanctioned by the US.

On January 26, the US Department of Treasury announced an extended list of Russian individuals and companies subject to sanctions imposed on Moscow over the Ukraine crisis, which included Power Machines (PM), the EPC contractor of Long Phu 1 thermal power plant.

The US’s embargo on PM directly impacts Long Phu 1 project. American contractors directly affected by the embargo unilaterally announced cancelling their contracts, including subcontractor General Electric (USA) which would have provided steam turbines and generators – the two most important equipment of the project.

The remaining contractors have been indirectly affected by the inability to trade in dollar, and many international banks from Italy, Germany, and Korea (except the two banks from Russia: VEB and IIB) declined to conduct payment transactions with PM.

Under the terms of the EPC contract, PM is responsible for assisting the investor in working with the bank to arrange an Export Credit Agreement (ECA) of $740 million while the rest of the EPC contract value would come from commercial loans. The amount of loans from Russian banks would include a maximum of $100 million in loans without government guarantee from International Investment Bank (IIB) and about $213.48 million from Vnesheconombank (VEB).

Since the US announced the embargo on PM, PetroVietnam and the management board of the project have immediately held meetings with the PM-PTSC joint venture, subcontractors, Russian banks, and international banks to discuss solutions to continue project implementation.

With the current difficulties, PetroVietnam asked the government to send an official dispatch requesting the Russian government, Ministry of Energy, and Ministry of Economic Development to instruct Russian banks to arrange the missing project capital. Also, Russian banks should build a payment mechanism for the EPC contract of Long Phu 1 Thermal Power Plant in USD to avoid risks and exchange costs for PetroVietnam and PM.

In addition, PetroVietnam recommended the government to direct the State Bank of Vietnam to instruct PetroVietnam in converting the payment currency of the EPC contract from USD to RUB and/or VND in case the US maintains the sanctions.

Whether the project will stick with PM or look for another contractor remains a question. Whether the solutions for the project work or not, the US embargo's bad effect on PM will still delay the construction of Long Phu 1. In addition, if the proposal to adjust the total project investment is approved, the project's selling price will increase to VND1,747.7 ($0.076) per kWh, higher than the current retail price of VND1,715.8 ($0.074) per kWh.

vir



NEWS SAME CATEGORY

VN logistics tangled up in red tape: CIEM

Red tape must be removed for domestic logistics firms to develop and compete in a market which had great potential, driven by a boom in international trade, but was...

People before products at Panasonic

At a time of vast social and ­economic changes within the 4.0 era, the business philosophy of Panasonic Corporation founder Konosuke Matsushita still holds true...

New forum on reform and development to be kicked off in December

As Industry 4.0 unfolds in Vietnam, the country’s new development vision will be discussed at an upcoming first-ever annual forum on reform and development.

Bao Minh textile project to fulfil gap in textile dyeing

Bao Minh textile factory, which is invested by Bao Minh Textile (JSC and will officially go on stream in October 2018, is expected to make great contributions to...

Project seeks to make textile sector more green

A project to make the textile industry more environment-friendly has been launched in Ha Noi by the World Wide Fund for Nature and the Viet Nam Textile and Apparel...

Vietnamese firms display fashion products at Hong Kong fair

Thirty-five leading manufacturers of handicrafts, garments, textiles, and fashion accessories and garment-related industries in Viet Nam are displaying their...

VITAS works with WWF to green Vietnam’s apparel sector

The World Wildlife Fund (WWF) and the Vietnam Textile and Apparel Association (VITAS) launched a project on October 26 to green Vietnam’s textile-apparel sector...

EU’s tariff evasion, dumping probe looms over Vietnamese tire manufacturers

The European Commission (EC) is considering an investigation into whether Vietnamese bus and truck tire exporters are avoiding tariffs or employing unfair...

Fair of industrial and consumer goods opens in Hoa Binh

More than 200 booths are displaying products at an exhibition of industrial and consumer goods that opened in the northern province of Hoa Binh on Thursday.

Year’s 3rd Vietbuild opens in HCM City

The latest products and services in housing, architecture and interior and exterior decoration are on display at the Vietbuild International Exhibition that opened...


MOST READ


Back To Top