Two petrochemistry projects stopped by authorities because of long delays

Dec 5th at 10:21
05-12-2016 10:21:42+07:00

Two petrochemistry projects stopped by authorities because of long delays

Shortly after the $22 billion petrochemistry & oil refinery project in Binh Dinh province was withdrawn by local authorities because of delay, another project in Can Tho has been stopped for the same reason.

 

The 2 million ton per annum Can Tho Oil Refinery was granted an investment certificate in May 2008. The investors – a joint venture between the Vien Dong Investment & Trade JSC and Semtech Ltd B.V.I, - registered the investment capital of VND8.608 trillion, or $538 million, in which the former contributed 30 percent of capital and the latter 70 percent.

Later, Semtech Ltd B.V.I left the joint venture because of financial problems. Vien Dong found a new partner - Razeedland Plaza (M) SDN. BHD, Brunei Darussalam, and the new joint venture got approval from city authorities in June 2015.

Prior to that, the Binh Dinh province announced the termination of the Nhon Hoi petrochemistry & oil refinery project, a mammoth project, with registered capital of $22 billion. Explaining the decision, the local authorities said the investor – PTT Group from Thailand – delayed the project and made claims which could not be satisfied by the government of Vietnam.

As such, except the operating Dung Quat Oil Refinery in Quang Ngai province, Vietnam still has four other valid oil refinery projects, namely Nghi Son in Thanh Hoa province, capitalized at $9 billion, Vung Ro in Phu Yen province ($3.2 billion), Nam Van Phong in Khanh Hoa province ($8 billion) and Long Son in Ba Ria-Vung Tau province ($4.5 billion).

Of these, the Long Son project has been delayed for eight years because of many reasons. Meanwhile, Qatar Petroleum, a partner of the project, withdrew from the project in 2015.

Despite commitments by investors, no one can say for sure if the projects would continue to be implemented.

As for Vung Ro project, for example, Technostar Management Limited, the investor, promised to put the refinery into operation by 2016 after 10 years of delay. However, it is obvious that the promise cannot be fulfilled.

In case of Nam Van Phong, the investors and local authorities still have not reached an agreement about the investment incentives to offer to the project.

Meanwhile, experts have warned that PetroVietnam, the national oil & gas group, would have to offset VND1.8-2.5 trillion ($80-110 million) in annual losses for Nghi Son oil refinery when it starts operation because PetroVietnam pledged to acquire Nghi Son oil products.

vir



NEWS SAME CATEGORY

Pigs call first dibs on feed

AGRO-Industrial conglomerate Mong Reththy Group inaugurated its first feed mill on Friday, with the factory’s production line aimed foremost at supplying the...

Chinese firm eyes steel mill

One of China’s largest steelmakers is seeking partners in Cambodia to build a steel mill that will reduce the Kingdom’s dependency on imported steel for its...

Angkor Gold agrees to buyback of mine NSR

Canadian mining firm Angkor Gold has agreed to an all-shares buyback of the net smelter return (NSR) interests on a mine in Ratannakiri province that it sold to...

Vietnamese oil firm still on track to drill in 2017

A government official yesterday denied local media reports that it had received a request from Vietnamese state-owned PetroVietnam Exploration Production...

Prospect for a budding industry

With Cambodia’s traditional cash crops struggling to compete in global supply chains, the Kingdom could carve out a lucrative niche in commercial cannabis...

PTT fuel to power up PAPA’s new business

PAPA Petroleum, the fledgling fuel distribution business of timber baron Try Pheap, has signed a fuel purchase agreement with PTT Global Chemical Plc, a subsidiary...

Deeper water expected to yield more fish

Just weeks ahead of the main fishing season on the Tonle Sap river, which supplies the majority of the fish used in the Kingdom’s traditional cooking sauce, prahok...

Minebea readies third factory

Japanese electronics manufacturer Minebea expects to complete construction of its third factory in Cambodia by the end of the year, allowing the company to...

Golden FX inks central counterparty contract

Golden FX Link yesterday signed an agreement with the derivative brokerage firm FUGI Gold allowing traders to continue to use its services.

Call for affordable electricity

Cambodia's electricity sector needs to focus on adopting the latest technology to reap the full benefits of its coal-fired and hydropower plants if the government...


MOST READ


Back To Top