The Quang Ngai People’s Committee resolutely proposed the government to end the long-delayed Guang Lian Steel-Dung Quat project, despite the investor Guang Lian Steel Viet Nam Co., Ltd.’s-a joint venture between Taiwanese enterprises Tycoons and E-United Group - proposal to restart the construction.

Licensed in September 2006, the project was initiated by Taiwanese steel giant Tycoons with a total investment of more than $556 million. The investor committed to completing the construction within 36 months.

E-United Group joined the project later by acquiring a 90 per cent stake. The two Taiwanese enterprises raised the registered investment amount to $3 billion in 2008 and then $4.5 billion in 2010, while simultaneously increasing the factory’s manufacturing capacity to seven million tonnes per year, five million tonnes higher than the initial capacity.

At the beginning of 2012, Japanese steelmaker JFE Group signed a memorandum of understanding with E-United Group to conduct a feasibility study on the project.

However, after two years of studies, the Japanese enterprise decided to withdraw from the steel project, leading to E-United Group’s proposal to reduce the investment amount to $2 billion. However, the local authorities refused the proposal due to their suspicion about the project’s feasibility.

In June 2015, the management board of Dung Quat Economic Zone asked Guang Lian Steel Viet Nam Co., Ltd. to prove its capability to continue implementing the steel project. The management warned the company to revoke its investment certificate unless the company proves its solid financial background before the end of June 2015.

The decision came after multiple delays in the investment process and the company’s failure to arrange the required capital.

As a result, in mid-2015, Tycoons out of the blue called a halt to the project due to difficulties in its finances and product consumption. Thus, the management board of Dung Quat Economic Zone proposed the prime minister to revoke the investment certificate.

In December 2015, the management board carried out an inspection of the project, while simultaneously requesting the investors to voluntarily liquidate the project’s assets.

In March 2016, the two investors submitted a document to the authority, committing to restarting the project with the total capital of $2.2 billion and an output of five million tonnes per year. The investors also committed to completing the construction within 42 months.

However, after numerous delays, the local authorities have grown distrustful of the investors as well as the very feasibility of the project.

Since its ground-breaking ceremony in 2007, the investors have put in about $42 million in constructing some work facilities, such as house blocks for workers, walls, and installing pile driving equipment.

vir



NEWS SAME CATEGORY

Clearing US technical trade hurdles

With the total volume of agriculture imports reaching $117 billion annually, the US market is any exporters’ dream market. However, fierce competition and technical...

Improved partnership brings trade bonanza

Trade is one of the keystones of the comprehensive partnership between the US and Vietnam. Bilateral trade has grown from nothing on the day Vietnam and the US...

TPP to usher in a new chapter of partnership and prosperity

In anticipation of US President Barack Obama’s visit to Vietnam, Virginia Foote, president of the International Center, chairwoman of AmCham Hanoi, and CEO of Bay...

Investing in the future

As climate change has ratcheted up in increments of severity in Vietnam over recent years through storms, flooding, and saline inundation, Vietnam and the US are...

US’ FDI in Vietnam

Vietnam has massive opportunities for attracting foreign direct investment, in particular, investment from the US, which is predicted by some to become the...

Reconciliation paves the way for partnership

At a press briefing following bilateral talks with US President Barack Obama on July 7, 2015, Vietnam Party General Secretary Nguyen Phu Trong stated that it is...

The extraordinary road to normalisation

Vietnam and the US have passed many commendable co-operative milestones along their 21-year journey since normalisation. Pete Peterson, the first US Ambassador to...

UPS Vietnam: “Helping local businesses benefit from Vietnam-US economic ties”

Vietnam-US economic relations have come a long way since 1995 when the normalisation of diplomatic relations opened up new trade opportunities for both markets.

Indochina Capital breaks new ground

Veteran American investor Peter Ryder reveals the ongoing development plan of Indochina Capital in Vietnam while reflecting on more than 20 years of investing in...

Geleximco pursues philosophy of “synthesising resources, sharing successes”

After more than two decades of development, the Hanoi General Export Import JSC (Geleximco) has now become one of Vietnam’s leading private business groups.


MOST READ


Back To Top