Xepian Xenamnoy dam on schedule in southern Laos

Jun 2nd at 15:22
02-06-2015 15:22:00+07:00

Xepian Xenamnoy dam on schedule in southern Laos

Construction of the Xe-Pian Xe-Namnoy hydroelectric dam is now over 17 percent complete after work began in February this year in Champassak and Attapeu provinces.

The Lao Holding State Enterprise (LHSE) reported yesterday that 17.18 percent of the project had been completed by April 30. This included the main Xepian and Xenamnoy dams and five other small dams built to block or cut valleys (saddle dams).

Construction of the headrace tunnel is also complete, along with the power intake, powerhouse, switchyard and two substations generating 230kV and 115kV.

LHSE said the remaining work consisted of installing high voltage transmission lines, hydraulic steel structures and electrical and mechanical equipment.

The project is slated for completion at the end of 2018 and commercial operation is set to commence in February 2019.

The entire project has an investment budget of about 8.16 trillion kip (US$1,020 million) with the work being carried out by the Xepian Xenamnoy Power Company (PNPC).

PNPC is a joint venture between SK Engineering & Construction Co Ltd (SKEC) and Korea Western Power Co Ltd (KOWEPO), Rachaburi Electricity Generating Holding PCL (RATCH) of Thailand, and LHSE.

LHSE holds a 24 percent stake in the venture, RATCH has a 25 percent shareholding, SKEC holds 26 percent, and KOWEPO 25 percent.

The project spans several catchments in Champassak and Attapeu and will take water from the Xenamnoy reservoi r. “The project will have a total reservoir area of 5,360 hectares,” the Champassak provincial Energy and Mines Department reported recently.

The dam will have an installed capacity of 410MW, with 40MW for local consumption and 370MW for export.

There will be a 110km double circuit 230kV transmission line from the powerhouse to the Pakxe substation in Champassak, and a 60km 500kV double circuit transmission line from the Pakxe substation to the delivery point in Thailand.

Once complete, the project is expected to supply about 1,823GWh of electricity per annum, providing revenue to Laos through taxes, royalties and dividends.

The project will generate over 1 trillion kip (US$135 million) in earnings per annum over its projected 27 years of operation.

PNPC signed a concession agreement for the project with the Lao government in October 2012.

The government is promoting the rapid development of power plants for local supply to reduce the need to import electricity.

Twenty-seven power plants are currently operational in Laos with a combined installed capacity of 3,304MW.

Laos is aiming for a total installed capacity of about 12,000MW by 2025, a report from the Ministry of Energy and Mines states.

The abundant resources of the Mekong River and its tributaries give Laos the potential to produce more than 25,000MW of electricity.

vientiane times



NEWS SAME CATEGORY

Xekong hydro plant study delayed

The feasibility study on the proposed Houay Yeung 7 hydropower project in Xekong province will not be completed on schedule but the provincial authorities have...

Hongsa power plant to start energy generation next month

Energy investor Lao Holding State Enterprise (LHSE) has reported that the coal-fired Hongsa Mine-Mouth Power Project is now testing its generator unit 1 after the...

Vientiane province to build new small power plant

Local and foreign energy developers hope to start construction this year of a small scale hydropower plant project, Keng Luang, in Kasy district of Vientiane...

Investor to construct power plant on Nam Mone

Nam Mone Hydropower Company has decided to develop a small hydropower plant on the Nam Mone river in Vangvieng district, Vientiane province.

More power plants to begin commercial operation

The Ministry of Energy and Mines reports that about eight power plants that are currently under construction will be complete by the end of this year, with total...

Namhoung 1 dam construction contracts signed

Simeuang Group Company Limited, project owner of the Namhoung 1 hydropower plant, has signed a construction agreement with three Korean contractors to build the...

Govt to regulate wood processing industry

Wood processors in Laos will be required to become members of an officially recognised association or group so they can be allowed to continue operating their...

EDL has huge outlay to reduce power cuts

Electricite du Laos (EDL) spent more than 20.8 billion kip last year on the maintenance, upgrade and installation of transformers and transmission lines to reduce...

DPM: Lower electricity production cost needed

Laos is enjoying rapid economic growth from the contributions of many sectors who play essential roles in the nation's development, none more so than electricity...

Hydropower major revenue earner for the country

As investment in the power generation sector continues to grow, the government is keen to see the hydropower industry produce 50 percent of the country's potential...


MOST READ


Back To Top