Vietnam kicks off US$400 million hydropower project

The plant will become one of two largest hydropower plants in Southeast Asia once put into operation by 2024.

Vietnam Electricity (EVN) has begun construction of a VND9.22 trillion (US$400 million)-hydropower extension plant that is located on Da River or Black River.

Overview of Hoa Binh Hydropower Extension Plant. Source: EVN

The investment for Hoa Binh Hydropower Extension Plant includes 30% of the investor and 70% from Joint Stock Commercial Bank for Foreign Trade of Vietnam (Vietcombank) and the Agence Française de Développement (AFD).

A consortium of domestic contractors namely the Ministry of National Defence’s Truong Son Construction Corporation, Construction Joint Stock Company 47, and Lilama 10 Joint Stock Company will build the extension plant capacity 480 megawatts (MW).

Once put into operation in 2024, the extension will raise Hoa Binh Hydropower Plant to 2,400 MW, equal to Son La Hydropower Plant, the largest hydropower project in Southeast Asia.

Upon completion, three hydropower plants on Da River namely Hoa Binh Hydropower Plant, Son La Hydropower Plant, and Lai Chau Hydropower Plant will have total capacity of 6,000 MW, contributing 30% of the country’s electricity output.

Prime Minister Nguyen Xuan Phuc at the ground-breaking ceremony of the hydropower extension plant. Photo: Quang Hieu

“We kick off Hoa Binh Extension Hydropower project as part of efforts to tap potential of the water resources to contribute to the country’s development,” Prime Minister Nguyen Xuan Phuc said at the ground-breaking ceremony early this week.

Big hydropower projects on Da River symbolize Vietnam’s industrialization and modernization, the PM said.

The construction of Hoa Binh plant must be absolutely safe for the sustainable development, especially the downstream areas, PM Phuc emphasized.

EVN’s General Director Tran Dinh Nhan said the Hoa Binh plant is aimed to make full use of Da River and utilize abundant water in flood seasons to work at highest capacity and ensure safety for the national grid.

Hoa Binh Hydropower Plant was built between November 1979 and December 1994 with design, equipment, and support by the USSR. It took the makers twice for river closure in 1983 and 1986.

With storing capacity 9.8 billion cu.m of water, the plant helps regulate water and prevent floods for the Red River Basin and Hanoi.

After more than 30 years of operations, the plant has supplied nearly 250 billion kWh.

Hanoi Times





NEWS SAME CATEGORY

Ho Chi Minh City waives half of market space rental for local vendors

Relevant agencies in Ho Chi Minh City will halve retail rentals for July-December 2020 at traditional markets, a policy expected to provide the much-needed support...

Korean firm expands tire cord plant in Vietnam

Kolon Industries, an industrial materials producer of the Republic of Korea (RoK), on January 12 said it will expand its tire cord plant in Vietnam to increase...

Manufacturing hub dreams manifesting with big moves

Vietnam is pushing ahead in its mission to become the ideal manufacturing hub for overseas investors by taking advantage of a largely pandemic-free landscape and...

Regional specialities programme sales of many products for Tet

Many products made under a programme called ‘One Commune One Product’ that facilitates the development of regional specialities will be sold through major retail...

Fertiliser companies smell success ahead in 2021

Fertiliser businesses have been predicted to flourish this year thanks to many positive supporting factors.

Vietnam to launch competitive retail electricity market in 2023

Vietnam Electricity will conduct price marketization to encourage investment in electricity industry and follow the State-regulated market mechanism.

PetroVietnam must continue as role model: PM

 Prime Minister Nguyen Xuan Phuc on Monday said the Viet Nam Oil and Gas Group (PetroVietnam) needs to remain a role model in expanding markets, optimising...

Two more Vietnamese dairy producers licensed to export to China

The Asia-Africa Market Department under the Ministry of Industry and Trade announced that the General Administration of Customs of China would continue issuing...

Construction of expanded Hoa Binh hydropower plant kicks off

The 480MW expansion of Hoa Binh hydropower plant will increase its total capacity to 2,400MW.