Red tape hindering power plant projects

May 13th at 15:50
13-05-2017 15:50:33+07:00

Red tape hindering power plant projects

Substandard investment procedures and regulations hinder investors in major power plant projects, baodautu.vn reported.

 

\Ngo Quoc Hoi, Director of An Khanh Thermal Power Company told the investment e-newspaper that investment procedures and policies for power plant investors overlapped.

For example, some projects were submitted with detailed information as part of the adjusted National Power Development Plan VII from 2011-2020, which was approved along with the projects in 2016.

However, once the projects were launched, investors were required to re-submit the project’s feasibility study, ask for assessments from ministries and agencies and then ask for Government approval.

“It takes an additional six to eight months for a duplicate process before the project is approved again,” Hoi said.

Domestic investors also complained about unequal treatment between independent power producer (IPP) projects and foreign-invested projects under Build-Operate-Transfer (BOT) contracts.

An IPP or non-utility generator is an entity, which is not a public utility, but which owns facilities to generate electric power for sale.

Foreign-funded BOT projects are given incentives in foreign currency exchange and power sale guarantees but domestic IPP projects are not.

If investors of IPP projects want to exchange currency to pay loans, they have to register with the State Bank and are at risk of changing exchange rates.

Hội added that domestic power investors faced difficulties in borrowing money from local banks.

The company’s Bac Giang Thermal Power Plant Project is set to be completed in 2022 with a capacity of 650 MW. This required investment of more than US$1 billion, which proved difficult to secure.

The company had to ask for loans from various banks as State Bank regulations only allowed a bank to provide loans to a customer worth a maximum of 15 per cent of its capital.

As a result, a big bank in Viet Nam like BIDV can lend a project about VND7.3 trillion (US$321.14 million) at most while an engineering-procurement-construction contract for a power plant is at least VND22 trillion.

“The rate should be increased to 25 per cent or power projects will face funding shortages as it’s not easy to mobilise loans from multiple banks,” Hoi said.

He also asked for a guarantee that Electricity of Việt Nam would buy power from IPP projects so that the projects could easily access loans.

Deputy Minister of Industry and Trade Hoang Quoc Vuong said the ministry had proposed the Government exempt investors from re-submitting feasibility studies if their projects were in the adjusted National Power Development Plan VII.

On differences between policies for IPP projects and foreign BOT projects, Vượng said that few local investors could afford $1 billion for a 650MW power plan or $2 billion for a 1,000-1,200 MW plant.

Thus, it was necessary to call for foreign investment and preferential treatment for foreign BOT projects was needed, he said.

He added that once energy investment demand fell and domestic investors were stronger, there would be no difference between policies for foreign and local investors.

bizhub



NEWS SAME CATEGORY

Travel firms’ revenues outstrip profits

Viet Nam’s tourism industry recorded a successful year with VND400 trillion (US$17.6 billion) of total revenue in 2016. However, the travel companies’ profits are...

Vietnam province fears ‘another Formosa’ as paper mill raises environmental concerns

With the fish death disaster caused by wastewater dumped by a steel plant into the waters off central Vietnam still fresh in the minds of citizens, administrators...

Viet Nam retail on cusp of change

The Vietnamese retail industry is on the cusp of great change, experts say.

Domestic private sector barred from power market

Currently, complicated procedures and regulations have become a barrier preventing domestic private investment from pouring into large-scale power plants.

Besra banished from Bong Mieu gold mine

The authorities of the central province of Quang Nam said that they would not propose the Ministry of Natural Resources and Environment to license Bong Mieu Gold...

Paint, printing ink industry to grow 6-8 per cent annually

Viet Nam’s paint and printing ink industry is expected to grow at 6-8 per cent in 2016-20, according to the industry business association.

PetroVietnam records 10 millionth oil barrel in Algeria

PetroVietnam Exploration and Production Corporation (PVEP) on Monday recorded its 10 millionth oil barrel at Block 433a & 416b of the Bir Seba mine in the Sahara...

VN textile sector urged to diversify raw material import sources

The Vietnamese textile and garment industry needs to diversify its raw material import sources if it wants to develop, a senior industry figure has said.

VN’s sugar inventory reaches record high in April

Total sugar inventory at factories and trading companies by the end of April reached a record high in the history of the local sugar industry, according to the Viet...

Da Nang approves first-ever dairy project

The central city has approved its first-ever dairy farm on 124ha in Hoa Phong commune in Hoa Vang district.


MOST READ


Back To Top